RESCHEDULED: Memorial Parkway Bridge Construction

FTM file. 
An abnormally rainy May has caused a delay in the closure of the Memorial Parkway bridge.

A bridge restoration project on the KY 1120 that crosses over I-471 is re-scheduled to begin Monday, May 16 due to the forecast. The project calls for the bridge to be closed to traffic and pedestrians for a 60 day period starting June 20.

Beginning Monday, motorists and pedestrians will encounter intermittent lane closures. The I-471 NB on-ramp (Exit 4) is scheduled to be closed from May 23 – June 6.   The I-471 exit-ramp (Exit 4) is scheduled to be closed from June 6 – June 20.  The full closure of the bridge will be June 20 – August 15.


Construction was originally slated for Wednesday, May 11. Officials noted that the construction schedule can change and is weather dependent.