Two local projects by Sanitation District 1 are about to launch in Newport. These projects will help to improve the flow of storm water in the area.

The first project will take place along Route 9 and last from approximately Spring 2021 to Fall 2021. This project will impact pedestrian traffic on the Fourth Street bridge. 

The second project will take place on Saratoga Street near Newport on the Levee and last until April 2021.

State Route 9 Realignment Project


Sanitation District No. 1 and the Kentucky Transportation Cabinet (KYTC) are working together to improve drainage in Newport as part of KYTC’s State Route 9 realignment project.


Providing Christian, compassionate, kind, exceptional care for your loved one. 
513-907-9007


The project includes the construction of 388 linear feet of separate storm sewer along Route 9 and extending through the earthen levee to discharge directly to the Licking River. SD1 will construct various access structures and gates to keep the Licking River from backing up into the storm pipe when the river level is elevated.

The partnership allows SD1 to upsize the separate storm sewers within the footprint of the State Route 9 realignment project. The upgrades will accommodate the separation of 197 acres of drainage from the surrounding areas.

By installing long-term sewer upgrades in connection with the road improvement project, KYTC and SD1 will minimize road disruptions while reducing overland flooding and improving water quality.

“This gives SD1 and the City of Newport flexibility to solve future drainage needs, in addition to seeing a combined sewer overflow (CSO) reduction,” said Ralph Johnstone, SD1 chief engineer.

Separating the sewer system will eliminate approximately 10 million gallons of typical-year CSOs, moving SD1 closer to its Clean H2O40 amended consent decree goal of recapturing 85 percent of all typical-year CSO volume by the year 2040.





KYTC will reimburse SD1 for bidding and managing the construction of the storm sewer, estimated to cost $1.77 million. After completion, SD1 will own and maintain the storm sewer.

“Projects like this benefit everyone,” said Bob Yeager, chief engineer of the Covington Division of KYTC. “There’s no reason to tear up the road a second time, and SD1 can increase sewer capacity for growth in the Commonwealth.”

SD1 estimates construction will begin in spring 2021 and continue through fall 2021, pending board approval. The sewer improvements will complete the overall Route 9 road improvement project.

While the earthen levee is excavated, walkers will not be able to use the walkway located on top of the levee to access the Fourth Street Bridge. Signs will be posted.

Separate Storm Water Pipe from Sanitary Sewer Pipe near Newport on the Levee

Sanitation District No. 1 will soon begin work on the final phase of a project to separate storm water pipe from sanitary sewer pipe near Newport on the Levee. 





During this final phase of a project that started in 2018 with the installation of a separate storm water pipe through the earthen levee to the Ohio River, additional storm sewer will be installed along Dave Cowens Drive and Washington Street. This will complete the separation of storm and sanitary sewer pipe along Washington Avenue south to East 9th Street and Saratoga Street south to just past East 7th Street.

Once this final phase is completed, the sewer separation will eliminate 15 million gallons of typical-year combined sewer overflow (CSO) in the area, moving SD1 closer to its Clean H2O40 goal of recapturing 85 percent of typical-year Northern Kentucky CSO volume by the year 2040.




The project, at a total cost of $957,054, will also increase capacity in this area of Newport, improving drainage conditions and reducing the potential for flooding and building backups. The project will also promote redevelopment in the urban corridor by softening storm water management requirements due to the creation of a separate system.

“This separation project is another example of SD1’s commitment to maximizing the impact of our work in Northern Kentucky,” said SD1 Executive Director Adam Chaney. “While accomplishing our Clean H2O40 goals is important, we also regularly look for opportunities to reduce flooding and backups and promote growth and development. This project checks all of those boxes.”

The project is expected to be completed by April 2021.